Increasing tank capacity by adding shell rings or courses
Dismantling of old tanks
Repair or replacement of tank bottom plate
Repair to tank foundation
Erection of other circular structures such as reactor shields in nuclear power stations, etc
Our Valued Clientele
PROJECT
SITE LOCATION
M/S Larsen & Toubro Elektotek
Oman
M/S Cylingas Co. LLC
Dubai
M/S Okz Holding Baltija
Lithuvania
M/S Punj Llyod
Singapore
M/S National Engineering Company
Tanzania
M/S Quality International LLC
Dubai
M/S Tanigra Contractor
Tanzania
M/S Overseas Manufacturing Co.
Singapore / Malaysia
M/S Danem Engineering Co
Dubai
M/S Tech Hard Building Material
Dubai
M/S Albanae Engineering Co.
U.A.E
M/S Vellath Engineering International
Sharjah
M/S Ab Montuotojas Panevezyje
Lithuania
M/S Oman Steel
Oman
M/S Al-Jadee Shamali Est
Dammam
M/S Agra
Kuwait
Our Advantage
Safety First Hydraulic Jacking System is the safest way to erect storage tank. The complete work is executed on ground level preventing risks of accidents. For decades, there has been not a single report which goes to prove its credibility in being the safest and most preferred method for storage tank construction. The popularity of hydraulic jack system has now discarded the need for a tall boom crane.
No Scaffolding Required
The jacking system requires various scaffolding and attachments to provide comfortable access for welding heights, but now all weldings can be done at ground level.
Easier Inspection
Welding inspectors can now perform ultrasonic or other non destructive tests on welds at ground level, which facilitates ease of inspection for better quality control. No more climbing up to perilous positions for welding inspectors.
Faster Erection
The shell plates are erected at ground level instead of being installed at the height of about 30 feet or more, saving construction time required for alignment of plates. The time and manpower required for lifting the plates to the height is eliminated. Construction work remains unaffected by rain or snow, since most work is done under the protection of the tank itself.
Tank Erection Top Downwards Cuts Construction Time And Cost Considerably :
New shell plates are constructed at ground level instead of being hauled up to about 30 feet heights or more, saving considerable time required for alignment of plates. The cumulative time required for lifting of men and material to heights is eliminated. Tank construction work remains practically unaffected by rain or snow, since most work is performed under the protection of the tank itself.
Most of the fabrication work is performed at ground level allowing for faster erection and reducing the risk of possible injuries
Eliminates the requirement of the crane
Faster erection
Cost of jacking equipment can be easily recovered after construction of 3 to 4 storage tanks or by erecting about 1200 tons of tankage. Jacking cost is approximately USD 50 per ton for 1200 tons
Example : Tank of 30 m diameter weighing about 300 tons needs 30 jacks of 12 ton each. Full cost of jacking equipment can be recovered in 4 such tanks.
Model Description 510-35D 2510-50D Working Capacity (metric tons) 12 25 Testing load (metric tons) 18 37.5 Standard arc distance between jacks (m) 1.80 to 3.0 Max plate height for which jacking equipment can be supplied (m) 2.5 or 3.0 or more Min plate height that can be used (m) 1.40 Min safe bearing capacity below trestle base plate (N/mm2) 1.45 Plate thickness range (mm) 6 - 40 8 and above Unitary climb (cm/stroke) 10 Time per stroke (minutes) Approx 5 Working pressure (kg/cm2) 120 135 Retracting system spring hydraulic
Why Us? / Our Strengths
Bell Hydromatics offers truly global capacity in designing and manufacturing of advanced hydraulic machines and equipment. The company specializes in hydraulic jacks that find application in almost every industry like : Machine Tools, Steel Mill, Injection Molding Machine, Presses, Marine, Fishing, Defense, Aero Space, Constructions & Air port ground supporting equipment. It expertises in providing customized solutions engineered to meet the unique requirements of the customers.
To Increase The Volume Of Existing Capacity Of Storage Tank
Dismantling/Cutting Existing Storage Tanks
Bottom Plate Repair/Replacement
Highlights
equipment is supplied with singe jack lifting capacities of
8 tons
12 tons
25 tons
Standard jacking equipment can be used for minimum shell plate width (height) of 1400 mm. and maximum of 2500 mm
For shell plates of more than 2500 width (height), jacking equipment can be supplied against specific requirements
Storage tanks with different types of roof (floating roof, fixed roof, suspended deck roof, column supported roof)
Gasholder tanks Horton spheres or spherical tanks for storage of propane, ammonia in gaseous form
Cryogenic tanks for storage of propane, ammonia at cryogenic temperatures
Smallest diameter of tank erected using jacking equipment : 6 mtrs*
Largest diameter of tank erected using jacking equipment : 92 mtrs*
Maximum weight of tank erected using jacking equipment : 1900 tons*
Dimensions of some tanks that have been actually erected using jacking equipment are:
Advantages & Applications
Safety FirstHydraulic Jacking System is the safest way to erect storage tank. The complete work is executed on ground level preventing risks of accidents. For decades, there has been not a single report which goes to prove its credibility in being the safest and most preferred method for storage tank construction. The popularity of hydraulic jack system has now discarded the need for a tall boom crane.No Scaffolding RequiredThe jacking system requires various scaffolding and attachments to provide comfortable access for welding heights, but now all weldings can be done at ground level.Easier InspectionWelding inspectors can now perform ultrasonic or other non destructive tests on welds at ground level, which facilitates ease of inspection for better quality control. No more climbing up to perilous positions for welding inspectors.Faster ErectionThe shell plates are erected at ground level instead of being installed at the height of about 30 feet or more, saving construction time required for alignment of plates. The time and manpower required for lifting the plates to the height is eliminated. Construction work remains unaffected by rain or snow, since most work is done under the protection of the tank itself.Tank Erection Top Downwards Cuts Construction Time And Cost Considerably :New shell plates are constructed at ground level instead of being hauled up to about 30 feet heights or more, saving considerable time required for alignment of plates. The cumulative time required for lifting of men and material to heights is eliminated. Tank construction work remains practically unaffected by rain or snow, since most work is performed under the protection of the tank itself.
Most of the fabrication work is performed at ground level allowing for faster erection and reducing the risk of possible injuries
Eliminates the requirement of the crane
Faster erection
Cost of jacking equipment can be easily recovered after construction of 3 to 4 storage tanks or by erecting about 1200 tons of tankage. Jacking cost is approximately USD 50 per ton for 1200 tons
Example : Tank of 30 m diameter weighing about 300 tons needs 30 jacks of 12 ton each. Full cost of jacking equipment can be recovered in 4 such tanks.
Model Description
510-35D
2510-50D
Working Capacity (metric tons)
12
25
Testing load (metric tons)
18
37.5
Standard arc distance between jacks (m)
1.80 to 3.0
Max plate height for which jacking equipment can be supplied (m)
2.5 or 3.0 or more
Min plate height that can be used (m)
1.40
Min safe bearing capacity below trestle base plate (N/mm2)
1.45
Bell Hydromatics Tank Jacking Equipments Are Used For
Construction, Dismantling, Repairs, Replacement, Maintenance of Tanks, Changing of Tank foundations, Tank base plates
Fixed Cone Roof Tank
Dome Roof Tank
Double Walled Tanks
Floating Roof Tanks
Column Supported Roof Tank
Spherical Tanks
Description
A tank jacking unit illustrated in the adjacent figure, consist of:
SHELL PLATE
HYDRAULIC JACK
SLIDING CHAIR
LIFTING ARM
LIFTING LUG
GUIDE LUG
VERTICAL TRESTLE
JACK ROD
ADJUSTABLE STAYS
BASEPLATE
Salient Feature
Bell Hydromatics Tank Jacking equipment are:
8 MT, 12 MT, 20 M X 25 MT Capcity
Standard models suitable for 2500 mm shell width
Special models available for higher shell width
Manufactured under strict quality control norms
Tested at 1.5 times rated capacity
Trained operators are deputed for operation
Tank Construction Methodology:
First foundation is completed, base/bottom plates and top most shell plates are erected and welded. Roof structural, roof plates & top angle ring welded for truss supported roof tanks
Tank jacking equipment erection is complete and hydraulic connections are complete with the power pack
On energizing the power pack the shell plates along with roof is lifted by the hydraulic Jacks to the required height
Next shall course plates are erected and welded
Jacking units are lowered and connected to the new shell plates and operation is repeated for balance shell course
After the last shell course plates are welded in position, the jacking units are dismantled. Shell to bottom plates welding is completed
Advantages
Welding done at ground level
Easy access for inspecting quality of welding at each stage
Roof is fixed to the top shell plate from the commencement, rendering it stable against WIND-LOAD throughout the erection work
Guide trestles stabilise the tank at the bottom maintaining its circularity and accuracy
Need of scaffolding is eliminated
HIGHEST SAFETY achieved as working is carried out at ground level
ECONOMY – cost effectiveness achieved as labour & time required is minimised
Technical Data
Kindly furnish the following details to determine the no. of units required for a Tank.
Project Location
Type of Work
Tank size (OD x HT)
Number of Tanks
Tank Weight (Shell)
Shell width (max)
Type of Roof and weight
Maximum / normal wind velocity
About Us
Bell Hydromatics is the leading hydraulic equipment manufacturer of hydraulic equipments,hydraulic tank jacking equipments, industrial hydraulic equipment, hydraulic systems and cylinders, hydraulic jack, lifting jack, tank jack, electrical operated jack, hydraulic power jack since the last one and half decade. With a team of dedicated engineers and highly skilled workforce“Bell Hydromatics” has always endeavored to satisfy their customers ever widening demands with unmatched precision.With the latest in-house machinery and infrastructure under one “Bell Hydromatics” is manufacturing a wide range of hydraulic equipments and industrial hydraulic equipment of different size and capacities according to customer''s request.
Bell Hydromatics is now not only manufacturing hydraulic equipments and industrial hydraulic equipment but also exporting their products to meet demands the world over and can proudly say that their products are now being used in the oil and gas refineries, power generation, chemical and fertilizer fields, etc.
Bell Hydromatics stands for precision & durability.